gantt
dateFormat MM-DD
title Fall 2024
todayMarker off
section Project Proposal
Work on proposal :active, 09-26, 10-18
Break down proposal :done, 09-26, 1d
Finalize project idea :done, 10-02, 1d
Present idea to advisor :done, 10-03, 1d
Review proposal : 10-17, 1d
section Fall Design Poster
Work on poster : 11-01, 11-15
Break down poster : 11-01, 1d
Review poster : 11-14, 1d
section Preliminary Design Report
Work on report : 11-16, 12-07
Break down report : 11-21, 1d
Review report : 12-05, 1d
section Other
Order needed supplies :active, task1, 09-30, 10-31
Set up servers : task2, 10-28, 2w
Run attacks on servers : task3, after task2, 3w
Design visual of attacks : task5, 11-18, 3w
CyberSecurity Visualization Timeline
Gantt Chart
gantt
dateFormat MM-DD
title Spring 2025
todayMarker off
section Team Contract Update
Work on contract : 01-20, 01-31
section EXPO Abstract & Poster
Work on abstract & poster : 02-01, 03-28
Break down abstract & poster : 02-01, 1d
Review abstract & poster : 03-26, 1d
section Capstone EXPO
EXPO Date : 04-25, 1d
section Final Design Report
Work on report : 03-29, 05-02
Break down report : 03-29, 1d
Review report : 04-30, 1d
section Other
Order needed supplies :active, task1, 01-13, 01-31
Set up servers : task2, after task1, 2w
Run attacks on servers : task3, after task2, 3w
Design visual of attacks : task4, after task3, 3w